for details

Sunday, February 28, 2010

resource-mobile tower erection prerequesite

KMBR 1999
CHAPTER XIX
TELECOMMUNICATION TOWERS
131. Distance form road and boundaries.- (1) The base of the tower or poles shall have minimum 3 metres distance from the plot boundary abutting the road, whether it is proposed on land or over a building, even if the building is having less than 3 metres distance:
Provided that the distance from road boundary of the accessory rooms such as equipment rooms, shelters, or generator rooms proposed over a building shall be that of the building.
(2) In addition to the distance specified under sub rule (1), set back required for road widening proposed in any Town Planning Scheme shall also be provided.
(3) Distance from other boundaries of the plot to the base of the telecommunication tower Or Pole structure or accessory rooms shall be minimum 1.20 metres:
Provided that if the telecommunication tower or pole structures or accessory rooms are proposed over a building, the distance from the boundaries other than that abutting a road; shall be that of the existing building;
Provided further that if the building abuts any plot boundary and the telecommunication tower or pole structures or accessory rooms are also proposed to abut that boundary then consent of the owner of the plot on the abutting side shall be obtained and produced along with the application for permit:
Provided also that no portion of the telecommunication tower pole structure or accessory room shall project or over hang into the neighbouring plots.

134. Electrical line clearance.- Every tower or ancillary construction shall satisfy the minimum vertical and horizontal clearance from electrical lines as stipulated in the Indian Electricity Act, 1910 and Indian Electricity Rules, 1956 as amended from time to time and also any regulation issued by the State Electricity Board.
THE INDIAN ELECTRICITY RULES, 1956
Chapter VIII
OVERHEAD LINES, UNDER GROUND CABLES AND GENERATING
STATIONS
79. Clearances from buildings of low and medium voltage lines and service lines-
(1) Where a low or medium voltage, overhead line passes above or adjacent to or
terminates on any building, the following minimum clearances from any accessible point, on the basis of maximum sag, shall be observed: -
(a) For any flat roof, open balcony, verandah roof and lean-to-roof-
(i) When the line passes above the building a vertical clearance of 2.5 metres from the highest point, and
(ii) When the line passes adjacent to the building a horizontal clearance of 1.2 metres from the nearest point, and
(b) For pitched roof-
(i) When the line passes above the building a vertical clearance of 2.5 metres immediately under the lines, and
(ii) When the line passes adjacent to the building a horizontal clearance of 1.2 metres.
(2) Any conductor so situated as to have a clearance less than that specified in sub-rule (1) shall be adequately insulated and shall be attached at suitable intervals to a bare earthed bearer wire having a breaking strength of not less than 350 kg.
(3) The horizontal clearance shall be measured when the line is at a maximum deflection from the vertical due to wind pressure.
1[Explanation- For the purpose of this rule, expression “building” shall be deemed
to include any structure, whether permanent or temporary]
139. Building to be authorised.- Erection of any telecommunication tower or pole structures or accessory rooms shall be permitted only over authorised buildings.
142. Completion Certificate.- (1) After completion of the work of the telecommunication tower or pole structure and accessory rooms as per permit, the applicant and the engineer shall submit to the Secretary completion certificate as in Form E and Form F respectively, along with a certificate of structural safety/stability of the tower and the building, if the tower or pole is constructed over a building.
(2) The secretary shall, if satisfied that the work has been completed as per permit, issue use certificate as in Appendix H allotting a number, included in a different series from that allotted to buildings, on the basis of which the authorities concerned may allow power connection, etc. for use of the service].